Auyin News

1st May 2023

Sea & Sky May Construction Update

We have plunged right into quarter two of 2023 with some very exciting progress at Sea & Sky.

Following on from the excitement of the topping off last month, with more structural updates. Level 4 and 5 have now all been stripped and the roof lift lids have been poured, as well as the north canopy on the roof.

Ground floor, level 1 and 2 are now all fully plastered and the window installation has been completed.

Level 3 has had metal studs and all windows installed, as well as high level plaster completed and the rough-in of services.

Level 4 apartments have also had metal studs and windows installed, as well as the rough-in services.

Construction is on track to be completed Q4 2023.