April has started off on a high for the team at Sea & Sky. At the end of March, we celebrated the official topping off of Sea & Sky.

Topping off means that the external structural works have been completed for all levels, and the internal works on each levels, including electricals, plumbing, painting, tiling, cabinetry are now all beginning.

On the ground floor internal plaster, tiling and wardrobes have been completed. The Façade cladding has been installed on the level 1 and 2. Level 1 and 2 have had windows installed and internal plaster completed.

Level 3’s internal plaster is underway, with windows installed and internal framing. Level 4 stripping is underway as well as the internal framing. Level 5’s stripping is currently underway.

Construction is on track to be completed Q4 2023.